Compressor Pads

Compressor Pads, Bonanza, AB

Project Overview

  • Constructing 2 – 1,700 sq/ft 1m thick Compressor Pads in Bonanza AB during winter months.

Project Highlights

  • Installed 7km of 35MM rebar throughout the pads.
  • Surveyed and placed 30 embed plates and 69 anchor bolts in each pad (with a 2 mm tolerance).
  • Trucked in over 400 meters of concrete, poured, and finished both pads in two days.